Rawatbhata: India on Monday began construction of its 25th atomic power plant.
However the first pour of concrete ceremony, which signals the beginning of the construction of a nuclear plant, was attended by Atomic Energy Commission Chairman Srikumar Banerjee and Nuclear Power Corporation of India Limited (NPCIL) CMD Shreyans Kumar Jain.
The concrete is being poured at the rate of 90 cubic metres per hour and at a controlled temperature of 19 degree Celsius. To monitor the temperature, ice is being mixed with the concrete.
The 700 MW PHWR, designed by NPCIL by scaling up its 540 MW PHWRs under operation at Tarapur since 2005, is expected to be completed in the next five years.
|